Scrum PSPO PSPO-I Question # 3 Topic 1 Discussion

PSPO-I Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

When can Developers cancel a Sprint?

(choose the best answer)


A.

When functional expectations are not well understood.


B.

When the selected Product Backlog items for the Sprint become unachievable.


C.

They cannot. Only Product Owners can cancel Sprints.


D.

When the Product Owner is absent too often.


E.

When a technical dependency cannot be resolved.