Scrum PSPO PSPO-I Question # 19 Topic 3 Discussion

PSPO-I Exam Topic 3 Question 19 Discussion:
Question #: 19
Topic #: 3

Which statement best describes the Sprint Review?

(choose the best answer)


A.

It is a mechanism to control the Developers activities during a Sprint.


B.

It is used to congratulate the Developers if they complete their forecast or to punish

the Developers if they fail to meet their forecast.


C.

It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and

figure out what to do next.


D.

It is a demo at the end of the Sprint for everyone in the organization to check on the

work done.