Question #: 39
Topic #: 5

When Developers are having trouble delivering an Increment because they do not understand a

functional requirement, what should they do?

(choose the best answer)


A.

Partially complete the functionality, and discuss the remaining work at the Sprint

Review.


B.

Add a specialist to the Development Team.


C.

Collaborate with the Product Owner to determine what is possible and acceptable.


D.

Defer the work to a more appropriate Sprint.