If the Scrum Team cannot complete its work by the end of the Sprint, the Sprint does not get extended. Instead, the unfinished Sprint Backlog Items go back to the Product Backlog and can be addressed in the following Sprint12. This approach allows the team to get better at estimating and reduces complexity due to the consistency of the Scrum Events2. The Scrum Team continuously learns and adapts12.