Scrum PSPO PSPO-I Question # 51 Topic 6 Discussion

PSPO-I Exam Topic 6 Question 51 Discussion:
Question #: 51
Topic #: 6

What are two effective ways for the Scrum Team to make non-functional requirements visible?

(choose the best two answers)


A.

Add them to the Product Backlog to ensure transparency.


B.

Run the integration and regression tests before the end of the Sprint, and

capture the open work for the Sprint Backlog of the next Sprint.


C.

Add them to the Definition of Done so the work is taken care of every Sprint.


D.

Put them on a separate list on the Scrum board, available for all to see.