Scrum PSPO PSPO-II Question # 19 Topic 2 Discussion

PSPO-II Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

Which of the following are advantages of a Product Goal that is well-understood by the Scrum

Team?

(choose the best three answers)


A.

A Product Goal is not mandatory in Scrum.


B.

It helps the Scrum Team keep focus and they can check any decision against it.


C.

It provides overall direction so Sprints will feel less like isolated pieces of work.


D.

It makes it easier to inspect incremental progress at the Sprint Review.


E.

It helps the Scrum Team to forecast when the entire Product Backlog will be

delivered.