Scrum PSPO PSPO-II Question # 20 Topic 3 Discussion

PSPO-II Exam Topic 3 Question 20 Discussion:
Question #: 20
Topic #: 3

How much of the Sprint Backlog must be defined during Sprint Planning?

(choose the best answer)


A.

Enough so the Developers can create a forecast of what they can do during the

Sprint.


B.

All of the potential work. Sprint Planning is not over until 100% of the work is

identified and estimated.


C.

Just enough to understand design and architectural implications.


D.

Just enough tasks for the Scrum Master to be confident in the Developer's

understanding of the Sprint.