What is one step when determining initial team capacity during PI Planning?


A.

Add together all of the points from recently completed Features


B.

Compare final team capacity across all teams


C.

Ensure Product Owner/Product Manager approval for all time-based capacity adjustments


D.

Subtract one point for every team member's vacation day, public holiday, or training day