Scrum Advanced Scrum Master SAFe-SASM Question # 1 Topic 1 Discussion

SAFe-SASM Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

How is team performance calculated in SAFe?


A.

The ratio of tasks planned to tasks completed


B.

The ratio of business value achieved to business value planned for the PI


C.

The ratio of Story points completed to Story points planned in the PI


D.

Team member utilization as a percentage of total capacity