WIP (Work in Process):Refers to the number of work items that are in progress at any given time.
Impact of High WIP:Having too many items in progress can lead to context switching, inefficiencies, and delays, ultimately slowing down the overall throughput of the team.
Throughput:The rate at which the team completes work items. Reducing WIP helps the team focus on completing tasks, leading to faster throughput and better flow of work.
SAFe Scrum Master References:
SAFe emphasizes limiting WIP to improve flow efficiency, reduce bottlenecks, and increase throughput.