Scrum Advanced Scrum Master SAFe-SASM Question # 6 Topic 1 Discussion

SAFe-SASM Exam Topic 1 Question 6 Discussion:
Question #: 6
Topic #: 1

What are two timestamps required to measure lead time when using a Team Kanban board? (Choose two.)


A.

When the Story is released to users and validated


B.

When the Story is deployed


C.

When the Agile Team pulls a Story onto the board


D.

When the Story is accepted by the Product Owner


E.

When the team completes validation of the Story