ServiceNow CIS-Strategic Portfolio Management CIS-SPM Question # 16 Topic 2 Discussion

CIS-SPM Exam Topic 2 Question 16 Discussion:
Question #: 16
Topic #: 2

When creating a project from demand, what related records are moved and copied upon Project Creation?


A.

Resource Plan and Cost Plan.


B.

Resource Plan and Change Requests.


C.

Idea and Demand.


D.

Cost Plan and Assessment.