Question #: 6
Topic #: 1

How are changes usually categorized in terms of implementation effort, which is calculated in days, in the Change Control Process of an automation project?


A.

Low, Medium, or High and it’s typically up to the company to decide on the number of days for each category.


B.

Easy, Moderate, or Complex and the company usually defines the timeframe for each of these categories.


C.

Changes are usually quantified in terms of the manpower needed rather than the number of days it takes to implement.


D.

Minor, Major, or Critical and it's usually the responsibility of the Project Manager to decide on the duration for these categories.