The planning phase is the foundational step in the SDLC where project strategy, objectives, and goals are defined.
Key deliverables include a high-level project roadmap, scope definition, and resource allocation plans.
Purpose of the Planning Phase:
Ensures all stakeholders agree on the project objectives.
Sets the stage for subsequent phases by identifying potential risks, timelines, and budgets.
Incorrect Options Analysis:
A. Corrections, additions, upgrades: Part of the maintenance phase.
B. Descriptions of features: Occurs in the design or analysis phase.
D. Checking interoperability: Occurs in the integration or testing phase.
References and Documents of Information Technology Management:
"SDLC Best Practices for Project Planning" (Gartner).
ITIL Framework for Project Planning (Axelos).