Questions # 1:

Who is responsible for managing the progress of work during a Sprint? (choose the best answer)

Options:

A.

The Scrum Master.

B.

The Product Owner.

C.

The Team Lead.

D.

The Project Manager.

E.

The Developers.

F.

All the above.

Expert Solution
Questions # 2:

You manage a product group in an organization. A Scrum Master is concerned with the very low availability of the Product Owner for her team. The Product Owner has subject matter expertise that is very difficult to duplicate or replace, but he has several other important responsibilities as well. The Scrum Master has discussed her concern with the Product Owner, but the Developers are still struggling to deliver value without additional guidance from the Product Owner. The Scrum Master is asking you for some guidance. What is the best way for you to help the Scrum Master? (choose the best answer)

Options:

A.

Help the Product Owner’s manager find a different Product Owner, who can dedicate the time needed, and help this new Product Owner come up to speed on the new product as quickly as possible.

B.

Help the Scrum Master to find a delegate who can join the Scrum Team to work with the Product Owner and represent business priorities when the Product Owner cannot be present.

C.

Recommend to the Scrum Master that she helps the Developers to do their best, document their decisions, and escalate problems to you.

D.

Offer to work with her, the Product Owner, and his manager, to find a way to ensure that the Product Owner's participation level is high enough to ensure that value can be delivered by the Scrum Team.

Expert Solution
Questions # 3:

True or False: The most important function of an Agile manager is to set goals and hold people accountable for their commitments.

Options:

A.

True

B.

False

Expert Solution
Questions # 4:

You manage a development organization. The Scrum Master of one of the Scrum Teams you are responsible for requests that you only communicate with the team through her. What do you do? (choose the best answer)

Options:

A.

Agree to her request, yet indicate that there may be occasions where you may still communicate directly with the Scrum Team. As a leader, it is your responsibility to help the team retain focus.

B.

Do not agree to her request. Explain that management holds you accountable for the Scrum Team’s results, and that you need access to the team to fulfill your responsibilities.

Expert Solution
Questions # 5:

Which of the following is NOT true of cross-functional teams? (choose the best answer)

Options:

A.

The team spends less time waiting on people outside the team to get things done.

B.

Team members have a greater opportunity to deliver product increments that deliver value to users.

C.

Cross-functional teams help team members develop deep technical specializations.

D.

Cross-functional teams encourage team members to step outside their comfort zone to get things done.

E.

Team members have more opportunities to grow their skills by learning from others.

Expert Solution
Questions # 6:

You are a Product Owner. The Developers are close to the end of a Sprint and ask you for 3 extra days to complete their work. They feel that if they do not get the extra time, they might look bad in front of stakeholders, who are already skeptical of using an agile approach. What should you do? (choose the best answer)

Options:

A.

Cut back on testing, or leave some items incomplete, so long as the Developers can "substantially meet" their goal.

B.

Agree to extend the Sprint but ask the team to be more realistic when they plan Sprints in the future.

C.

Ask the Developers to work longer hours to meet their goal.

D.

Ask the Developers to commit to what was agreed and find a solution for the problem.

E.

Do not extend the Sprint and stick to the original timebox. Work with the stakeholders to explain why transparency and openness are important.

Expert Solution
Questions # 7:

What is an important responsibility of an Agile leader?

(Choose the best answer)

Options:

A.

Prioritize work; make sure that high-value work gets done.

B.

Ensure teams have what they need to succeed and help them to remove impediments.

C.

Set priorities, plan work, monitor progress, and take corrective action.

D.

Set Sprint Goals and make sure the team achieves those goals.

E.

Hire team members and organize teams.

Expert Solution
Questions # 8:

Which Scrum event most helps a Scrum Team to continuously improve? (choose the best answer)

Options:

A.

Sprint Planning.

B.

The Daily Scrum.

C.

The Sprint Retrospective.

D.

Refinement.

E.

The Sprint Review.

Expert Solution
Questions # 9:

You are the manager of a team, and a disagreement arises between Developers about the technical approach the team should use to solve a particular challenge. The debate gets quite heated, and there does not seem to be a compromise position. How should the team proceed?

(Choose the best answer)

Options:

A.

The Product Owner should decide which approach to take.

B.

The Developers should run an experiment to test the alternative approaches.

C.

You, as a manager, should decide which approach to take.

D.

The Scrum Master should decide which approach to take.

Expert Solution
Questions # 10:

One of the newest and least experienced Scrum Teams in your organization has 7 members: 3 are in London (UK), 1 is in Paris (FR), and 3 are in Mumbai (IN). What outcome would you expect? (choose the best answer)

Options:

A.

The team will likely need help with communication and knowledge sharing challenges.

B.

Each location should have an on-site Scrum Master.

C.

The cost of delivering the product will be significantly lower than if all team members were together in London (UK).

D.

Having team members in multiple locations actually increases productivity because the work can “follow the sun.”

Expert Solution