Exam DCDC-003.1 All Questions
Exam DCDC-003.1 Premium Access

View all detail and faqs for the DCDC-003.1 exam

Viewing page 4 out of 5 pages
Viewing questions 31-40 out of questions
Questions # 31:

What is the minimum slab floor to ceiling height recommended?

Options:

A.

12feetminimum

B.

14feetminimum

C.

15feetminimmum

D.

16feetminimum

Expert Solution
Questions # 32:

How far should Data Center be located from Commercial Airport?

Options:

A.

At Least 3 Miles

B.

At Least 5 Miles

C.

At least 10 miles

D.

None of the above.

Expert Solution
Questions # 33:

What is a possible downside to customer-owned maintenance holes?

Options:

A.

fire risk near data center property

B.

susceptibility to theft or damage by unauthorized personnel

C.

poor aesthetic appearance around facility exterior

D.

leaks leading to water infiltration into data center

Expert Solution
Questions # 34:

what are the dimensions of circulation pathways?

Options:

A.

4 feet wide and have clear overhead of 8 feet

B.

5 feet width with a height of 7feet.

C.

6feet width, width depends on the layout functionality.

D.

None

E.

All

Expert Solution
Questions # 35:

what is the second preference regarding utility service

Options:

A.

At least four circuits each from different distribution stations but fed via common feeders B. Two balanced feeds with different voltages derived from a single distribution station

B.

One balanced feeder coordinated with upstream backup feed D. At least One Circuit from two Separate Substations and Different Voltage Levels

Expert Solution
Questions # 36:

What is the recommended amount of fuel supply needing to be available to a class F2 data center?

Options:

A.

12 hours

B.

18 hours

C.

24 hours

D.

30 hours

E.

36 hours

Expert Solution
Questions # 37:

where should printers be located

Options:

A.

beside high traffic areas

B.

near equipment that has active air flow to cool them down

C.

in a dedicated print room with dedicated air handling system

D.

placed outdoor, away from building facilities

Expert Solution
Questions # 38:

What is the NEBS GR-3028-CORE recommended operational temperature.

Options:

A.

-25°F to +125°F (-32°C to +52°C)

B.

-30°F to +110°F (-34°C to +43°C)

C.

-20°F/-28° C minimum and up to a maximum of104 ° Fahrenheit/40° Celsius

D.

Up To140 Degrees Fahrenheit /60 Degrees Celsius

Expert Solution
Questions # 39:

when is a battery room required to have electrolyte spill containment and exhaust systems?

Options:

A.

when using Lithium batteries

B.

when using Nickel Cadmium batteries

C.

when using Sealed lead-acid-batteries

D.

when the batteries contain liquid, free-flowing electrolyte

E.

All of Above

Expert Solution
Questions # 40:

What is the minimum raised floor height?

Options:

A.

6"

B.

12"

C.

18"

D.

24"

Expert Solution
Viewing page 4 out of 5 pages