Questions # 131:

A company wants to move its data from on premises to off premises. Which of the following cloud models should be pursued?

Options:

A.

XaaS

B.

SaaS

C.

PaaS

D.

laaS

Expert Solution
Questions # 132:

Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written. Which of the following relationships best describes this scenario?

Options:

A.

Start-to-start

B.

Start-to-finish

C.

Finish-to-finish

D.

Finish-to-start

Expert Solution
Questions # 133:

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

Options:

A.

Work with the project scheduler to update the project timeline.

B.

Communicate to the stakeholders about the updated timeline.

C.

Ask the development team to fast-track upcoming activities.

D.

Add two resources so the critical activities will finish on time.

Expert Solution
Questions # 134:

Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project's timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?

Options:

A.

Smoothing

B.

Confronting

C.

Forcing

D.

Compromising

Expert Solution
Questions # 135:

A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?

Options:

A.

Creation of a social news forum

B.

Management directives to use the new system

C.

New user kickoff meeting

D.

Monthly feedback and training sessions

Expert Solution
Questions # 136:

Which of the following best represents an intellectual property breach?

Options:

A.

Internal developers use code from a legacy in-house system to develop a new solution for the marketing department.

B.

The price list to end customers was stored on a stolen external hard drive.

C.

A service provider that worked on a project uses the developed software on a project for a new customer.

D.

Customer data is stored on a shared network drive that is accessible by employees from all departments.

Expert Solution
Questions # 137:

A project manager buys an extended warranty for a set of servers. Which of the following risk management strategies is the manager using?

Options:

A.

Transfer

B.

Avoid

C.

Accept

D.

Mitigate

Expert Solution
Questions # 138:

A project manager needs to develop a way to control who can modify documents, artifacts, and other data related to the product. Which of the following would be the best way to accomplish this objective?

Options:

A.

Define access requirements.

B.

Develop a transition plan.

C.

Create a responsibility assignment matrix.

D.

Create a work breakdown structure.

Expert Solution
Questions # 139:

A software engineer notices that the newest update to the reporting software includes many new features that were not defined in the requirements document. Which of the following steps should the engineer take next?

Options:

A.

Seek approval before continuing

B.

Edit the requirements document

C.

Disregard the update

D.

Notify the users of the new features

Expert Solution
Questions # 140:

A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:

Question # 140

Which of the following issues should be addressed FIRST?

Options:

A.

Replace missing peripherals because this process can be easy and less costly.

B.

An old operating system issue has the most amount of occurrences.

C.

Damage to the monitor has the highest percentage.

D.

Address each issue as discovered to avoid rework.