AACE International Professional Level Certifications PSP Question # 2 Topic 1 Discussion

PSP Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

Which of the following is NOT true?


A.

Remaining durations can exceed original durations.


B.

Constraints can interfere with the longest path calculation.


C.

Multiple calendars can affect the total float calculation.


D.

A network must contain only one Critical Path.