Questions # 1:

What day would Activity C complete if the duration of Activity B was reduced to zero?

Options:

A.

50

B.

20

C.

30

D.

40

Expert Solution
Questions # 2:

Which of the following is NOT true?

Options:

A.

Remaining durations can exceed original durations.

B.

Constraints can interfere with the longest path calculation.

C.

Multiple calendars can affect the total float calculation.

D.

A network must contain only one Critical Path.

Expert Solution
Questions # 3:

What is the workweek period for this project?

Question # 3

Options:

A.

Monday through Friday

B.

Sunday through Friday

C.

Monday through Saturday

D.

Sunday through Saturday

Expert Solution
Questions # 4:

The data date or status date of a schedule represents the:

Options:

A.

date the monthly update is performed

B.

date the project manager turns in the schedule update

C.

system date when the software calculates the update

D.

date on which progress is based

Expert Solution
Questions # 5:

If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?

Options:

A.

8 days

B.

6 days

C.

4 days

D.

5 days

Expert Solution
Questions # 6:

Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?

Options:

A.

42.

B.

36.

C.

40.

D.

37.

Expert Solution
Questions # 7:

Why does activity 1001 have two successor activities?

Question # 7

Options:

A.

Because the late finish of 1001 and the late start of 7001 require two successors

B.

Because the problem could not effectively work with only one successor

C.

Because there are two defined logic paths for the work

D.

Because the duration of activities 2001, 2002 and 200.f require two successors

Expert Solution
Questions # 8:

The sum of all budgets for work scheduled to be accomplished within a given time period is the ____________.

Options:

A.

Estimate at completion (EAC)

B.

Budget at completion (BAC)

C.

Budgeted cost of work performed (BCWP)

D.

Budgeted cost of work scheduled (BCWS)

Expert Solution
Questions # 9:

Determine the correct formula and date for the late finish for Activity 9004.

Options:

A.

LF of 10002 less 24 days

B.

LS of 9004 plus 72 days

C.

LF of 8001 plus 72 days

D.

LS of 10002 less lag of 7 days plus 1 day equaling 20 Nov 2023

Expert Solution
Questions # 10:

A driving relationship is _____________________.

Options:

A.

A critical relationship.

B.

A finish-to-start relationship.

C.

The link between two related activities.

D.

The link between a predecessor and the activity whose dates it controls.

Expert Solution