Questions # 41:

Constraints control events or activities that __________________.

Options:

A.

Affect only the forward pass.

B.

Are not based on project relationships.

C.

Affect only the backward pass.

D.

May be over-ridden by activity logic.

Expert Solution
Questions # 42:

Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. what is indicated?

Options:

A.

The activities are independent, with Activity 4001 starting 15 days earlier than the start

of Activity 5001

B.

These activities are partially concurrent, with Activity 4001 starting 15 days after the

start of Activity 3001

C.

These activities are sequential, with Activity 4001 starting 15 days earlier than the start of Activity 3001.

Expert Solution
Questions # 43:

Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

Question # 43

Options:

A.

These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.

B.

These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.

C.

The activities occur in series with a 15-day lag.

D.

The activities run concurrently.

Expert Solution
Questions # 44:

The activity with the most total float is:

Question # 44

Options:

A.

Activity I.

B.

Activity C.

C.

Activity F.

D.

Activity D.

Expert Solution
Questions # 45:

Is activity 7001 pictured correctly in the precedence diagram?

Question # 45

Options:

A.

No, the total float is not shown correctly.

B.

Yes, except the early finish date is not shown.

C.

No, the start-to-start and finish-to-finish relationships are backwards.

D.

Yes, the duration is 48 days.

Expert Solution
Questions # 46:

Which of the following are NOT normally included in the project scope statement, either directly or by reference?

Options:

A.

Project objectives in terms of cost, schedule and quality measures

B.

Project contract between the contractor and owner

C.

Project justification

D.

Project deliverables

Expert Solution
Questions # 47:

Determine the correct formula and date for the late finish for Activity 6002.

Options:

A.

LS of 6003 plus 1 day equaling 09 Mar 2023

B.

LS of 6003 less 1 day equaling 09 Mar 2022

C.

LS of 6003 less 1 day equaling 09 Mar 2023

D.

LS of 6003 plus 1 day equaling 09 Mar 2022

Expert Solution
Questions # 48:

Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

Question # 48

Options:

A.

407 days

B.

362 days

C.

255 days

D.

267 days

Expert Solution
Questions # 49:

SUBCO is a potential concrete bridge contractor based in a metropolitan area 300 miles away from your project. They have offered to supply manpower and equipment t BILCO at a per diem rate of $3,000 above their direct labor and equipment rates. In doing a cost benefit analysis, which of the following is NOT a consideration?

Options:

A.

SUBCO direct labor and equipment rates

B.

BILCO liquidated damages in the SDOT contract

C.

Pending negotiations with GOUGE.

D.

The distance of SUBCO to your project

Questions # 50:

The project goals_________.

Options:

A.

are the foundation for breakdown structures

B.

are defined independent of any external stakeholder opinions

C.

quantify performance and interface requirements

D.

consider all aspects of the project