Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PSP All Questions
Exam PSP All Questions

View all questions & answers for the PSP exam

AACE International Professional Level Certifications PSP Question # 44 Topic 5 Discussion

PSP Exam Topic 5 Question 44 Discussion:
Question #: 44
Topic #: 5

Is activity 7001 pictured correctly in the precedence diagram?

PSP Question 44


A.

No, the total float is not shown correctly.


B.

Yes, except the early finish date is not shown.


C.

No, the start-to-start and finish-to-finish relationships are backwards.


D.

Yes, the duration is 48 days.


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.