Questions # 51:

Which of the following risks CANNOT be estimated by BILCO with only a resource-loaded schedule?

Options:

A.

Delay due to SDOT's other projects

B.

Delay due to labor shortage

C.

Liquidated damages on the SDOT contract

D.

Cost overruns due to cement shortage

Questions # 52:

Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

Options:

A.

15 days.

B.

0 days.

C.

5 days.

D.

10 days.

Questions # 53:

What is the actual duration as of the status date or data date of Activity B?

Question # 53

Options:

A.

7.

B.

3.

C.

0.

D.

4.

Questions # 54:

Total float is defined as the amount of time an activity can be delayed without impacting

Options:

A.

The overall project completion

B.

The buoyancy of a successor activity

C.

The next activity

D.

The end of that activity

Questions # 55:

Which of the following is the most important scheduling consideration for the BILCO contractual scope?

Options:

A.

Logical phasing lies

B.

Update frequency

C.

Conforming CPM schedule to SDOT standards

D.

Cost loading

Questions # 56:

Which of the following parties is NOT a stakeholder of the Spring Highway project?

Options:

A.

ALPHA

B.

GOUGE

C.

BILCO

D.

DEVCO

Questions # 57:

What does the heavy, vertical line at "X" represent?

Question # 57

Options:

A.

Delay fault line.

B.

The status or data date.

C.

Change-over limits.

D.

International Date Line.

Questions # 58:

Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?

Options:

A.

Subcontract outside forces to accelerate the Phase A Schedule

B.

Allocating forces from other BILCO contracts to the toll road project

C.

Proceeding with the work in advance of the environmental studies

D.

Reduce the phasing from 5 phases to 3 phases

Questions # 59:

Which of the following is NOT required when performing weekly or monthly schedule updates?

Options:

A.

Percent complete.

B.

Remaining duration of activities.

C.

Actual finish of activities.

D.

Original duration of activities.

Questions # 60:

The data date or status date of a schedule represents the:

Options:

A.

date the monthly update is performed

B.

date the project manager turns in the schedule update

C.

system date when the software calculates the update

D.

date on which progress is based