Questions # 61:

Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?

Question # 61

Options:

A.

Drafting and Proofing the Manual.

B.

Packaging only.

C.

Printing the Manual.

D.

Testing, Manufacturing and Packaging.

Questions # 62:

What portion of Activity B is on the critical path?

Options:

A.

Last half of the activity

B.

None of it

C.

First half of the activity

D.

The whole activity

Questions # 63:

Project delays are best analyzed

Options:

A.

After either the contractor or the owner acknowledges ^responsibility for the delay.

B.

Contemporaneously with the delay.

C.

By an expert after the project is finished when complete records are available and the impact is known.

D.

Late in the project.

Questions # 64:

Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?

Question # 64

Options:

A.

36 lifts

B.

24 lifts

C.

30 lifts

D.

48 lifts

Questions # 65:

Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?

Options:

A.

42.

B.

36.

C.

40.

D.

37.

Questions # 66:

Schedule forecasts are periodically conducted to project the project schedule performance at completion Which of the following situations would probably result in an incorrect forecast?

Options:

A.

The cost variance

B.

The profit or loss for the project

C.

The variance at completion

D.

The schedule variance

Questions # 67:

Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?

Question # 67

Options:

A.

$271,000

B.

$299,000

C.

$139,000

D.

$289,000

Questions # 68:

Project Life Cycle Phases do NOT include the following item:

Options:

A.

procurement

B.

budgeting

C.

design

D.

start-up

Questions # 69:

Using the normal schedule, what is the owner's total cost of the project?

Options:

A.

S13.990.600

B.

S12.990.000

C.

S13.102.900

D.

S12.953.600

Questions # 70:

A driving relationship is _____________________.

Options:

A.

A critical relationship.

B.

A finish-to-start relationship.

C.

The link between two related activities.

D.

The link between a predecessor and the activity whose dates it controls.