Questions # 31:

What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

Options:

A.

Use the progressed portion of the critical path of all the updates previous to the current update.

B.

Use the progressed portion of the critical path of the baseline schedule.

C.

Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.

D.

Use the forward-looking critical path of the most current updates.

Expert Solution
Questions # 32:

Project schedules help control all of the following EXCEPT for_____________________.

Options:

A.

Quality

B.

Cost

C.

Resources

D.

Time

Expert Solution
Questions # 33:

Resource planning must take all of the following into account except for:

Options:

A.

Types of materials, equipment and labor skills required to complete the project.

B.

Earned value techniques established for the project.

C.

Time available to complete the project.

D.

Cash flow (expenditure) limitations for completing work on the project.

Expert Solution
Questions # 34:

Which activity is drawn in the incorrect position?

Question # 34

Options:

A.

Activity G.

B.

Activity E.

C.

Activity C.

D.

Activity D.

Expert Solution
Questions # 35:

Which of the following is NOT input data to the construction planning process?

Options:

A.

Input from the owner

B.

The contract

C.

Bonding capacity of subcontractors

D.

Input from the contractor

Expert Solution
Questions # 36:

In a graphical earned value analysis, what time-scaled value determines the reporting intervals for both schedule and cost performance?

Options:

A.

Budgeted cost of work scheduled

B.

Budgeted cost of work performed

C.

Schedule performance index

D.

Actual cost of work scheduled

Expert Solution
Questions # 37:

The characteristic of the precedence diagramming method that models construction projects differently than the arrow diagramming method is that it____________.

Options:

A.

uses arrows to signify logic in a network

B.

allows more than one critical path to be represented

C.

can be used to calculate the late start and late finish of all activities

D.

allows multiple relationship types to be associated with activities

Expert Solution
Questions # 38:

The work breakdown structure is used to organize

Options:

A.

"Smart activity ID codes" representing similar items of scheduled work

B.

The chart of accounts

C.

Similar activity coding of schedule activities

D.

The smallest defined work packet

Expert Solution
Questions # 39:

Estimate to complete (ETC) is __________________.

Options:

A.

The expected remaining cost needed to complete an activity, group of activities or the project

B.

The costs actually incurred in accomplishing the work performed

C.

The expected total cost of an activity, group of activities or the project

D.

The value of the completed work expressed in terms of the budget assigned to that work

Expert Solution
Questions # 40:

What owner action could have mitigated the late completion of the project?

Options:

A.

Hire a more senior project manager.

B.

Self-perform more of the work.

C.

Use a procurement agent to monitor and expedite equipment deliveries.

D.

Prepare better structural steel drawings.

Expert Solution