Question #: 29
Topic #: 4

Resource planning must take all of the following into account except for:


A.

Types of materials, equipment and labor skills required to complete the project.


B.

Earned value techniques established for the project.


C.

Time available to complete the project.


D.

Cash flow (expenditure) limitations for completing work on the project.