AACE International Professional Level Certifications PSP Question # 33 Topic 4 Discussion
PSP Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4
The characteristic of the precedence diagramming method that models construction projects differently than the arrow diagramming method is that it____________.
A.
uses arrows to signify logic in a network
B.
allows more than one critical path to be represented
C.
can be used to calculate the late start and late finish of all activities
D.
allows multiple relationship types to be associated with activities
Chosen Answer: