Estimate to Complete (ETC) is the forecast of additional costs required to complete the remaining project work.
Option B refers to actual costs incurred (AC).
Option C refers to Estimate at Completion (EAC), which includes both actual costs and ETC.
Option D refers to Budgeted Cost of Work Performed (BCWP).
ETC is a critical concept for forecasting and project control as described in the PSP Study Guide.