AACE International Professional Level Certifications PSP Question # 27 Topic 4 Discussion

PSP Exam Topic 4 Question 27 Discussion:
Question #: 27
Topic #: 4

What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?


A.

Use the progressed portion of the critical path of all the updates previous to the current update.


B.

Use the progressed portion of the critical path of the baseline schedule.


C.

Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.


D.

Use the forward-looking critical path of the most current updates.