There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?

Time-scaled logic diagrams are
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.
What method offers the best chance of the schedule being used effectively to implement the project in the field?
The BEST reason to use multiple calendars is to:
Which of the following is NOT a tool or technique used to perform scope planning?
In a "crashed" schedule, which is a chain of activities that precede activity 2004?

For activity 11001. why would the crashed direct cost be greater than the direct cost of the normal schedule?
What is the result of a forward pass calculation?