Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PSP All Questions
Exam PSP All Questions

View all questions & answers for the PSP exam

AACE International Professional Level Certifications PSP Question # 19 Topic 3 Discussion

PSP Exam Topic 3 Question 19 Discussion:
Question #: 19
Topic #: 3

In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?


A.

The schedule has too much detail to reflect an accurate critical path.


B.

Different calendars are assigned to certain activities in the logical chain.


C.

The schedule is projecting an "early completion".


D.

Certain activities in the critical path have no successors.


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.