Forward Pass Calculation:
A forward pass determines the earliest start (ES) and earliest finish (EF) dates for all activities, progressing from project start to finish.
Total float is calculated later by comparing early and late dates.
PSP Study Guide References:
Forward and backward pass calculations are core elements of CPM scheduling methodology​.
Conclusion: The correct answer is B, as forward pass provides ES and EF for activities.