AACE International Professional Level Certifications PSP Question # 18 Topic 3 Discussion

PSP Exam Topic 3 Question 18 Discussion:
Question #: 18
Topic #: 3

Time-scaled logic diagrams are


A.

Only calculated using a computer.


B.

The same as a pure-logic diagram.


C.

Used to calculate the most probable activity duration.


D.

Logic networks that are drawn to match the calendar.