AACE International Professional Level Certifications PSP Question # 21 Topic 3 Discussion

PSP Exam Topic 3 Question 21 Discussion:
Question #: 21
Topic #: 3

What method offers the best chance of the schedule being used effectively to implement the project in the field?


A.

Issue detailed schedule updates as frequently as possible.


B.

Obtain consent and agreement to the schedule from the key project personnel.


C.

Include detailed and stringent set of scheduling specifications in the contract.


D.

Allow large time contingencies on milestones and completion deadlines.