AACE International Professional Level Certifications PSP Question # 24 Topic 3 Discussion

PSP Exam Topic 3 Question 24 Discussion:
Question #: 24
Topic #: 3

In a "crashed" schedule, which is a chain of activities that precede activity 2004?

PSP Question 24


A.

1001, 2001, 2002, 2003


B.

2001, 2002, 2003, 2007


C.

1001, 2002, 2003


D.

1001, 2002, 2002, 2003, 3001