Questions # 11:

What day would Activity C complete if the duration of Activity A was reduced by five days?

Options:

A.

35

B.

30

C.

45

D.

40

Expert Solution
Questions # 12:

What is the remaining work duration of Active D?

Question # 12

Options:

A.

4.

B.

11

C.

8.

D.

3.

Expert Solution
Questions # 13:

What is the cycle time?

Question # 13

Options:

A.

5 minutes

B.

17 minutes

C.

14 minutes

D.

6 minutes

Expert Solution
Questions # 14:

Budgeted cost of work scheduled is _______________________.

Options:

A.

The value of the completed work expressed in terms of the budget assigned to that work

B.

The total authorized budget for accomplishing the project scope

C.

The expected total cost of an activity, group of activities or the project

D.

The sum of all budgets for work scheduled to be accomplished within a given time period

Expert Solution
Questions # 15:

When resource leveling craft labor for a critical path schedule, the scheduler

Options:

A.

Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.

B.

Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.

C.

Need not consider its effects, as it is a theoretical concept with limited application to construction projects.

D.

Need only consider the non-union crafts persons.

Expert Solution
Questions # 16:

Determine the correct formula and date for the late start for Activity 9001.

Question # 16

Options:

A.

The early finish is required in order to determine the answer.

B.

LS.6001 Dur.6001 -> 11-20-02.

C.

There is insufficient data provided to calculate the answer.

D.

LF.9001 Dur.9001 -> 11-20-02.

Expert Solution
Questions # 17:

Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?

Question # 17

Options:

A.

91 days

B.

183 days

C.

193 days

D.

168 days

Expert Solution
Questions # 18:

Determine the correct formula and date for the late finish for Activity 2002.

Options:

A.

LS of 2003 less 1 day equaling to 06 Oct 2021

B.

LS of 2003 less 1 day equaling to 06 Nov 2021

C.

LS of 2003 plus 1 day equaling to 07 Oct 2021

D.

LS of 2003 less 1 day equaling to 05 Oct 2021

Expert Solution
Questions # 19:

What does the heavy, vertical line at "X" represent?

Question # 19

Options:

A.

Delay fault line.

B.

The status or data date.

C.

Change-over limits.

D.

International Date Line.

Expert Solution
Questions # 20:

Using a 1.75 cubic yard [1.34 cubic meter] bucket, how many lifts does it take to pour each 2.000-cubic foot [56.64 cubic meter] column?

Options:

A.

30 lifts

B.

133 lifts

C.

42 lifts

D.

60 lifts

Expert Solution