AACE International Professional Level Certifications PSP Question # 11 Topic 2 Discussion
PSP Exam Topic 2 Question 11 Discussion:
Question #: 11
Topic #: 2
When resource leveling craft labor for a critical path schedule, the scheduler
A.
Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.
B.
Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.
C.
Need not consider its effects, as it is a theoretical concept with limited application to construction projects.
Resource leveling adjusts start and finish dates of activities to resolve resource conflicts or constraints, balancing availability and demand.
In construction projects, breaks in continuity of work for subcontractors can result in increased costs due to remobilization and demobilization.
PSP Study Guide References:
The PSP guide explains that resource leveling must be carefully analyzed to avoid disruptions in work continuity.
Conclusion: The correct answer is A, as the scheduler must account for potential cost implications of resource leveling on subcontractors.