AACE International Professional Level Certifications PSP Question # 11 Topic 2 Discussion

PSP Exam Topic 2 Question 11 Discussion:
Question #: 11
Topic #: 2

When resource leveling craft labor for a critical path schedule, the scheduler


A.

Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.


B.

Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.


C.

Need not consider its effects, as it is a theoretical concept with limited application to construction projects.


D.

Need only consider the non-union crafts persons.