AACE International Professional Level Certifications PSP Question # 12 Topic 2 Discussion

PSP Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

Determine the correct formula and date for the late start for Activity 9001.

PSP Question 12


A.

The early finish is required in order to determine the answer.


B.

LS.6001 Dur.6001 -> 11-20-02.


C.

There is insufficient data provided to calculate the answer.


D.

LF.9001 Dur.9001 -> 11-20-02.


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.