Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

Exam PSP All Questions
Exam PSP All Questions

View all questions & answers for the PSP exam

AACE International Professional Level Certifications PSP Question # 38 Topic 4 Discussion

PSP Exam Topic 4 Question 38 Discussion:
Question #: 38
Topic #: 4

What day would Activity C complete if the duration of Activity A was reduced by five days?


A.

35


B.

30


C.

45


D.

40


Get Premium PSP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.