A cycle time includes all the operations needed for one complete lift:
Sling Up: 5 minutes
Hoist Up: 4 minutes
Discharge: 3 minutes
Clear Unload Area: 3 minutes
Hoist Down: 2 minutes
Calculate Total Cycle Time:
Cycle Time = 5 + 4 + 3 + 3 + 2 = 17 minutes.
Cross-Verification:
Option A (5 minutes): Incorrect. Excludes operations.
Option C (14 minutes): Incorrect. Underestimates.
Option D (6 minutes): Incorrect. Miscalculation.
Option B (17 minutes): Correct.