Late Finish (LF) is calculated by adjusting the Late Start (LS) of the subsequent activity (2003) by the lag value.
The formula, LS of 2003 - 1 day, aligns with CPM principles where the predecessor's LF must occur before the successor starts.
The date calculation, considering lags and dependencies, results in 06 Oct 2021.
References: PSP Study Guide, Section 2.2.4 – Relationships and Calculations, Appendix A – Sample Calculations for LF and LS relationships.