Scheduling Professional Study Guide and Documents References:The Budgeted Cost of Work Scheduled (BCWS) is the planned value of all tasks scheduled during a specific period. It is a measure used in earned value management to assess schedule adherence.
Option A defines Budgeted Cost of Work Performed (BCWP).
Option B defines the total project budget (BAC).
Option C defines the expected total cost, which is Estimate at Completion (EAC).
This answer is consistent with earned value methodologies and their application in project controls​​.