AACE International Professional Level Certifications PSP Question # 25 Topic 3 Discussion

PSP Exam Topic 3 Question 25 Discussion:
Question #: 25
Topic #: 3

For activity 11001. why would the crashed direct cost be greater than the direct cost of the normal schedule?


A.

Additional extended overhead is also being shown in this activity


B.

Some costs resulting from the crashed efforts were forgotten in previous activities


C.

Generally, more equipment is used for a crashed project; therefore, it costs more to demobilize


D.

Management bonuses for early completion were included in this activity