Question #: 36
Topic #: 5

What owner action could have mitigated the late completion of the project?


A.

Hire a more senior project manager.


B.

Self-perform more of the work.


C.

Use a procurement agent to monitor and expedite equipment deliveries.


D.

Prepare better structural steel drawings.