AACE International Professional Level Certifications PSP Question # 41 Topic 5 Discussion

PSP Exam Topic 5 Question 41 Discussion:
Question #: 41
Topic #: 5

Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

PSP Question 41


A.

These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.


B.

These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.


C.

The activities occur in series with a 15-day lag.


D.

The activities run concurrently.