A hammock activity spans over multiple activities and reflects the cumulative duration from the earliest start to the latest finish of the grouped activities.
Activities in the Hammock (6001–6003):
Activity 6001: Duration = 102 days, FS relationship with successor.
Activity 6002: Duration = 140 days, FS with 6001.
Activity 6003: Duration = 115 days, FS with 6002.
Calculate the Duration:
Earliest Start of Activity 6001 → Latest Finish of Activity 6003.
Total duration = 102 + 140 + 115 = 362 days.
Cross-Verification with Answer Options:
Option A: Incorrect. Overestimates.
Option C: Incorrect. Underestimates.
Option D: Incorrect. Underestimates.
Option B: Correct. Matches the calculated duration.