Question #: 5
Topic #: 1
If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?
Daily work hours per crew: 5 workers × 8 hours/day = 40 hours/day.
Duration = Total hours ÷ Daily work hours = 240 ÷ 40 = 6 days.
This calculation aligns with standard resource planning principles.