Teams using Project A and B currently use their own respective Scrum boards.
They must now work together on the same products and issues and in the same sprints.
You created a new Scrum board based on this filter:
project in (A,B) ORDER BY Rank ASC
You must also check two settings to make sure the teams can access and use the new board.
Identify the two settings. (Choose two.)