During the execution phase of a program a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects What should the program manager do to address the situation'?


A.

Review and update the detailed stakeholder list


B.

Review and update the stakeholder engagement plan


C.

Execute the component project's communications management plan


D.

Update the risk register.