As a project manager, what should the FINAL task be at of the end of each project?
The program manager defines the program objectives, requirements and develops a high-level road map. To ensure program alignment with the enterprise strategic plan the program manager should work with which of the following?
The program manager wants to ensure that a program contributes to shareholder value. The program manager should verify alignment with which of the following?
A program was kicked off, but one of the key stakeholders was not present at the kick-off meeting. What should the program manager do to ensure that the key stakeholder is familiar with the program's benefits and supports the program'?
Company A acquires company B. which leads to a two-year program lo integrate the processes and systems Company B uses a different project management process, and the company's staff is unhappy about the acquisition As a result company B's project team fails to provide status and cost data in a format that conforms to the program standards.
What should the program manager do first?
A program manager assigns project managers lo five component projects and continues to develop the program team. Which of the following represents the program manager's strategy?
A program manager is assigned to a large cross-functional program trial includes five different technologies and multiple workstreams.
Some potential stakeholders have conflicting program expectations
What should the program manager do next/?
The chief executive officer (CEO) informs the program manager that the delivery dale for protect A must be compressed by two months to accommodate market needs Project A relies upon deliverables from projects B and C.
Which of the following should the program manager do first?
Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule
What should the program manager do?
Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?