Questions # 1:

As a project manager, what should the FINAL task be at of the end of each project?

Options:

A.

A costing and billing review

B.

Delivery of the final documentation

C.

A lessons learned meeting

D.

A sign off meeting with the owner

Expert Solution
Questions # 2:

The program manager defines the program objectives, requirements and develops a high-level road map. To ensure program alignment with the enterprise strategic plan the program manager should work with which of the following?

Options:

A.

Program governance board

B.

Program management office

C.

Change control board

D.

Project managers on the program

Expert Solution
Questions # 3:

The program manager wants to ensure that a program contributes to shareholder value. The program manager should verify alignment with which of the following?

Options:

A.

Program charter

B.

Organizational structures and policies

C.

Organizational strategic objectives

D.

Program governance plan

Expert Solution
Questions # 4:

A program was kicked off, but one of the key stakeholders was not present at the kick-off meeting. What should the program manager do to ensure that the key stakeholder is familiar with the program's benefits and supports the program'?

Options:

A.

Note stakeholder communication needs in the program charter and document their expectations in the benefits sustainment plan

B.

Note stakeholder communication needs in the communications management plan and document their expectations in the benefits management plan

C.

Meet with the stakeholder to ensure stakeholder communication needs are documented in the communications management plan and that their expectations of benefits are documented in the benefits management plan

D.

Meet with the stakeholder to ensure stakeholder communication needs are documented in the communications management plan and that their expectations of benefits are documented in the benefits sustainment plan

Expert Solution
Questions # 5:

Company A acquires company B. which leads to a two-year program lo integrate the processes and systems Company B uses a different project management process, and the company's staff is unhappy about the acquisition As a result company B's project team fails to provide status and cost data in a format that conforms to the program standards.

What should the program manager do first?

Options:

A.

Inform the stakeholders of this Issue as soon as possible

B.

Change the program standards, aligning them with the project standards

C.

Work with the reports provided to extract the required information

D.

Remind the project manager of the relevant program standards

Expert Solution
Questions # 6:

A program manager assigns project managers lo five component projects and continues to develop the program team. Which of the following represents the program manager's strategy?

Options:

A.

Rotate the responsibility for risk assessment among the program components

B.

Coach the project managers to manage project resources

C.

Cross-train the project managers to share expertise

D.

Prepare the project managers to assume larger roles with more responsibility.

Expert Solution
Questions # 7:

A program manager is assigned to a large cross-functional program trial includes five different technologies and multiple workstreams.

Some potential stakeholders have conflicting program expectations

What should the program manager do next/?

Options:

A.

Conduct interviews with key stakeholders, and document the results in the program management plan

B.

Update the stakeholder register to document stakeholders' positions relative to the program

C.

Document stakeholder expectations in the program's risk register to determine their influence

D.

Send out satisfaction surveys and document the results in the program's stakeholder engagement plan.

Expert Solution
Questions # 8:

The chief executive officer (CEO) informs the program manager that the delivery dale for protect A must be compressed by two months to accommodate market needs Project A relies upon deliverables from projects B and C.

Which of the following should the program manager do first?

Options:

A.

Direct the three project managers to crash their projects to allow project A the two months of scheduling needed

B.

Review the program resource management plan with the three project managers emphasizing their critical paths and shared critical resources to understand the possibility of accelerating the schedule

C.

Convene the change board to evaluate the cost benefit of the compression and the impact on the overall program

D.

Engage the executive sponsor and program board to evaluate the CEO's request and determine if the project manager should act on it

Expert Solution
Questions # 9:

Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule

What should the program manager do?

Options:

A.

Join project-level issue resolution meetings to accelerate the decision-making process.

B.

Initiate discussions with the program governance board about assigning a more experienced project manager to the project

C.

Emphasize that the project manager needs to address the issues and follow up at the next scheduled meeting

D.

Develop an immediate corrective action plan with the project manager and coach them on decision-making responsibilities

Expert Solution
Questions # 10:

Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?

Options:

A.

Decompose the program work based upon available resources

B.

Decompose the program to the work package level

C.

Decompose the program lo the architecture baseline level

D.

Decompose the program at a level sufficient to achieve control

Expert Solution