Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Pass the BICSI RCDD RCDDv14.1 Questions and answers with ValidTests

Exam RCDDv14.1 All Questions
Exam RCDDv14.1 Premium Access

View all detail and faqs for the RCDDv14.1 exam

Viewing page 5 out of 10 pages
Viewing questions 41-50 out of questions
Questions # 41:

After taking over a program, a program manager reviews the program's status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs The program manager establishes earned value (EV) metrics and determines that the program has a budget of USS2.1 million, is three months into a nine-month timeline, and the planned value (PV) at the three-month point should be US$320,000. The program has spent US$350,000 and the EV is US$340,000

Based on this information, the program manager determines which of the following?

Options:

A.

The schedule is US%30.000 under budget

B.

The cost is US$20.0O0 under budget

C.

The schedule is US$10.000 over budget

D.

The cost is USS20.000 over budget

Expert Solution
Questions # 42:

An ICT distribution designer installed a 50/1 ?5 mm/1300 nm fiber optic cable from Building A to identical Building B with a distance of 600 m (1968 ft) At Building B. the designer fusion splice this new cable to an existing identical 50/126 mm fiber optic cable that runs 800 m (2525 ft) to Building C. Both ends are terminated with SC connectors. What is the loss budget for the above fiber link?

Options:

A.

2.95 dB

B.

3.40dB

C.

3.90 dB

D.

4.35 dB

Expert Solution
Questions # 43:

i program with six projects has been running for three years. The company's procurement and contracts department has compiled a qualified seller list. The program manager determines that one of the projects must be outsourced

he program manager will use the qualified seller list to do which of the following?

Options:

A.

Plan a proposal evaluation system

B.

Prepare the program procurement management plan

C.

Perform the required program budget updates

D.

Issue requests for proposals

Expert Solution
Questions # 44:

Identify the core switch(es) and server(s) of the data center in the diagram below by dragging the appropriate term into each box in the diagram.

Question # 44

Options:

Expert Solution
Questions # 45:

An organization initiates an innovation program to deliver exceptional performance and benefits. After the program transition plan is in place and the implementation of a benefits sustainment plan starts the program manager discovers the program may be shut down due to lack of funding.

To ensure continued funding for the program, what should the program manager do next?

Options:

A.

Complete the benefits sustainment plan and update the benefits register

B.

Present a revised ROl to the program sponsors based on the remaining investment.

C.

Conduct a cost-benefit analysis to ensure the program sponsors understand the program's long-term benefits

D.

Review the program business case and the program's strategic alignment and long-term benefits with the program governance board.

Expert Solution
Questions # 46:

A program manager has four projects pending approval Senior management asks the program manager to identity a project for potential elimination based on the return on investment. The program manager has the following information to guide and support the decision.

Which project should the program manager select to be cancelled?

Question # 46

Options:

A.

Project A

B.

Project B

C.

Project C

D.

Project D

Expert Solution
Questions # 47:

A project's closeout plan will be executed by the project manager (PM) and will be managed and approved by the

Options:

A.

owner

B.

contractor

C.

lCT distribution designer

D.

projects installation supervisor

Expert Solution
Questions # 48:

A program manager joins a team during its preparation phase. What should the program manager do lo obtain formal sponsor approval to begin the benefits delivery phase1?

Develop the program management plan based on the organization's strategic plan

D. Write the program charter, including the program mission statement and stakeholder engagement plan

C. Define a high-level program roadmap of milestones and schedules supported by a preliminary estimate

D. Identify and document the anticipated program benefits in the benefits management plan.

Options:

Expert Solution
Questions # 49:

One interior TTY must be provided at locations defined as public accommodations with ________ or more pay telephones.

Options:

A.

One

B.

Two

C.

Four

D.

Six

E.

Eight

Expert Solution
Questions # 50:

Which of the following transmitter light sources has a MINIMUM bandwidth of 4700 MHz/km (EMB) at 850 nm">

Options:

A.

OM1 (62 50/125 multimode)

B.

OM2 (50/125 multimode)

C.

OM3 (50/125 laser optimized multimode)

D.

OM4 (50/125 laser optimized multimode)

Expert Solution
Viewing page 5 out of 10 pages
Viewing questions 41-50 out of questions